News

21st December

Our latest project Fyfield Road achieved 2.4 ach just through good workmanship. This goes to show that all new builds should be achieving these levels at the very least.



11th November

New project alert! See our latest project York Street updated on our Selected Project tab.



22th October

Borisa Ristic & Co were involved in assisting Hill and Paul Jennings from Aldas in the snagging process of the airtightness layer at Agar Grove, to achieve the Passive House standard of 0.6 ach. Some photos of the work involved below.









4th September

Photos of our new project on Inkerman Road are now up. Have a look at the entire project here!



16th August

York Street project completed! More pictures coming soon...







18th June

Demolition on new project underway in Walthamstow...



5th May

Lockdown review of previous project... 1st floor refurbishment with bespoke joinery and lots of pipework!









22th February

Kitchen completed and a nice dark finish





12th January

The beautiful tones of reclaimed railway sleepers used for bookshelves!



25th November

Internal joinery material selection



12th November

Our current project with external wall insulation and lime pointing...



21th November

...and photovoltaic panels.



22nd October

Utility cupboards are important to be compact and well laid out!



20th October

Check out Falkland Road under our 'Selected Projects' section, here is a little teaser...



30th September

Pictures have come through of our last compeleted project in Chelsea, London





 

25th August

Our last project in Tufnell Park has been shortlisted for the Wood Awards and published in Grand Designs Magazine!



 

31st May

Our new approach to construction... a construction drawing in 3d. Brings all the details out!



 

April and May

Borisa Ristic & Co have been working alongside Kier and Encraft in Bristol to make 4 new terraced homes airtight.







 

12th February

Tufnell Park finishing touches...



 

5th February

Joiners are hard at work, shelving in the dining room is now in!



 

30th January

Rear facade has just had a makeover. A cheeky lead flashing.



 

10th January

Stainless steel island... orbital finish... ready to be delivered



 

5th December

Double height roof light at Hensford Gardens works!



 

26th November

Steelwork and drainage is in at Tufnell Park. Onwards with the extension...



 

14th November

A props forest. Without these, there would be very little left standing!



 

13th November

Hensford Gardens achieves airtightness rate of 0.6 ach! A Passivhaus standard on an existing building.



 

20th October

A team on a training day at the Passivhaus Tradesperson course at Saint Gobain.



 

30th September

Deep retrofit ideally means removing all of the existing internal walls. Beautiful!



 

9th September

Thanks to some skilful engineering the floor finish is also the structure.



 

20th August

If anybody is interested, how to tape up a joist hanger properly.



 

23rd July

Paul Jennings from Aldas undertaking the final airtightness test. Performance - 2.1ACH... pretty good.



 

18th July

Finally, the infinity glass arrived and fits perfectly!



 

15th June

The evening light casting some great shadows in the dining room rooflight



 

05th June

Full speed ahead!



 

19th May

Undertaking airtightness test before the walls are finished. It means any mistakes can be repaired.



 

15th May

A new spring, a new facade!



 

26th April

The benefits of using lime plaster is that it is breathable and it looks nice too.



 

10th April

The new exposed joists going in to the dining and kitchen spaces...



 

28th March

An internally insulated wall, airtight and ready to be plastered!



 

26th March

All penetrations into the external wall are sealed to ensure a high level of airtightness.



 

25th March

A small project given a much needed refresh!



 

16th March

140m2 of internal wall insulation delivered with a little help from our friends at NBT.



 

27th February

5 Swedish Houses air permeability test with Paul Jennings. Air permeability of 4.1m3/hr/m2 achieved.



 

22th February

Falkland Road soldiers!



 

19th December

Scaffolding down!



 

15th December

Internal wall insulation made from wood fibres allows for a nice breathable building.



 

27th November

Key services nice and air tight!



 

17th November

Our new project for an energy efficient home in Kentish Town is up and running.



 

05th November

A North London transformation!



 

29th May

Team talk...



 

10th May

The sunshine is out and the dormers are complete.



 

29th April

5 Swedish House has just received a coat of plaster with the stairs experiencing a new geometry!



 


16th April

Roof has been completed on Swedish House and we are watertight. Topping out ceremony soon...